252.236-7000 Modification Proposals—Price Breakdown (Dec 1991)
-
The Contractor shall furnish a price breakdown, itemized as required and within the time specified by the Contracting Officer, with any proposal for a contract modification.
-
The price breakdown—
-
Must include sufficient detail to permit an analysis of profit, and of all costs for—
-
Material;
-
Labor;
-
Equipment;
-
Subcontracts; and
-
Overhead; and
-
-
Must cover all work involved in the modification, whether the work was deleted, added, or changed.
-
-
The Contractor shall provide similar price breakdowns to support any amounts claimed for subcontracts.
-
The Contractor's proposal shall include a justification for any time extension proposed.
(End of clause)