@@ -27,7 +27,7 @@
|
|
|
27
27
|
<li class="- topic/li ">
|
|
28
28
|
<p class="- topic/p " id="d3572e26">
|
|
29
29
|
<ph props="autonumber" class="- topic/ph ">(b)</ph>
|
|
30
|
-
The Contractor will promptly advise the Contracting Officer if it finds that the project being designed will exceed or is likely to exceed the funding limitations and it is unable to design a usable facility within these limitations. Upon receipt of such information, the Contracting Officer will review the Contractor
|
|
30
|
+
The Contractor will promptly advise the Contracting Officer if it finds that the project being designed will exceed or is likely to exceed the funding limitations and it is unable to design a usable facility within these limitations. Upon receipt of such information, the Contracting Officer will review the Contractor's revised estimate of construction cost. The Government may, if it determines that the estimated construction contract price set forth in this contract is so low that award of a construction contract not in excess of such estimate is improbable, authorize a change in scope or materials as required to reduce the estimated construction cost to an amount within the estimated construction contract price set forth in paragraph (c) of this clause, or the Government may adjust such estimated construction contract price. When bids or proposals are not solicited or are unreasonably delayed, the Government shall prepare an estimate of constructing the design submitted and such estimate shall be used in lieu of bids or proposals to determine compliance with the funding limitation.</p>
|
|
31
31
|
</li>
|
|
32
32
|
<li class="- topic/li ">
|
|
33
33
|
<p class="- topic/p " id="d3572e31">
|